Vermont Public is independent, community-supported media, serving Vermont with trusted, relevant and essential information. We share stories that bring people together, from every corner of our region. New to Vermont Public? Start here.

© 2024 Vermont Public | 365 Troy Ave. Colchester, VT 05446

Public Files:
WVTI · WOXM · WVBA · WVNK · WVTQ · WVTX
WVPR · WRVT · WOXR · WNCH · WVPA
WVPS · WVXR · WETK · WVTB · WVER
WVER-FM · WVLR-FM · WBTN-FM

For assistance accessing our public files, please contact hello@vermontpublic.org or call 802-655-9451.
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

Explore our latest coverage of environmental issues, climate change and more.

Pipeline Protestors Hold Fish-In

Anti-pipeline activists launched a "fish-in" at the Public Service Board office in Montpelier this afternoon. They want construction of a natural gas pipeline halted while state regulators review a 40 percent increase in the project's cost estimate.

Demonstrators outside the Public Service Board office wore fishing garb and sang protest songs while sitting in a land-bound canoe. One of the protesters was Burlington resident Andy Simon, who is a Vermont Gas ratepayer.

"So we came together with the idea that this 40 percent cost increase represented a bait and switch on the part of Vermont Gas Systems," said Simon. "That they knew beforehand that construction costs were going to be considerably higher than what they had reported to the public service board when they got a Certificate of Public Good, back in December."

Vermont Gas announced earlier this month that the estimated cost of phase one of the project had climbed  to more than $121 million dollars. But Steve Wark, a Vermont Gas spokesman, says the project will still save energy consumers money, despite the increase.

"It’s currently under construction and it will bring $152 million in energy savings to up to about 4,000 customers in Addison," said Wark. "So put that in context, that will help people cut their heating bills in half, and a typical customers can save $1,000 to $2,000 a year."

The company attributes the higher costs to construction cost increases and route changes, to accommodate landowners and towns along the route.

Vermont Gas wants to extend its system from Franklin and Chittenden counties south, through Addison and Rutland counties, with a spur under Lake Champlain to serve the paper mill in Ticonderoga, New York.

Amy is an award winning journalist who has worked in print and radio in Vermont since 1991. Her first job in professional radio was at WVMX in Stowe, where she worked as News Director and co-host of The Morning Show. She was a VPR contributor from 2006 to 2020.
Latest Stories